Park Street Roundabout final pavement work, striping, and installation of light poles is anticipated to begin Monday, June 1, weather dependent. The work will occur 7 p.m. to 7 a.m. through June 4. Final striping is planned for the week of June 22nd.  

Pavement lifting will address the existing pavement transitions and standing water that occurs during heavy rains. This will bring the project to 95%, with removal of existing power poles and undergrounding of existing overhead being the final project.

If you have any questions about the project, please contact Mark Rigos, Public Works Director at mrigos@northbendwa.gov.